Monday, 30 April 2018

Belly Tanks Fuel

This blog covers the construction of the fuel delivery system for the belly tanks.

Overview
With both belly tanks fitted to the hardpoints a means of supplying fuel to the main tanks is required. In operation any given tank is run down to about 50% then the opposite side tank is selected and the fuel transfer pump turned on, fuel is then delivered to the tanks using the existing fuel return line.

Installation
Aeroflow fittings were used to construct the piping in conjunction with short loops of 3/8'' rubber fuel hose to allow flexibility in service and at installation. Two check valves are incorporated to prevent fuel traveling in an untended direction.





At the the hard points [rib #9] more aeroflow fitting in conjunction with a dry break valve. allowing the fuel line to be broken and re-connected without fuel spillage.





Two plug provide power for a fuel pump located in the belly tank along with a second to connect a Belight low fuel indicator to be incorporated into the tank. The tanks are yet to be offered by the factory but now is the time to install enough hardware to meet the future need.

Comment
These fittings are not cheap but they are a solution in a box and I am short on time.

Monday, 16 April 2018

Elevator - Upgrade

This blog covers the work to install stiffeners for the elevator bell-crank and discovering a hidden error.

Overview
Flying Legend asked me too install two [2] angle stiffeners at the rear bell crank which are now incorporated into the current air-frame, after inquiring on method they advised the best way was to remove the elevator stab. 

Installation
The first task involved removing the fairings, rudder, fin post and to expose the deck plate. 

All pop rivets were then removed followed by both deck plates and finally the bell crank to allow installation off the new stiffeners plus installing bushes into the bell-crank. All the new brackets were alodined and a trial fit showed the rivets on the original brackets attaching the bulkhead and stringers would now foul, so new brackets were required.

These were fabricated from 0.040'' 2024-T3 to allow countersunk rivets to be used which solved all the interference issues, these were alodined, riveted into position and another trial fit undertaken.

Note: This was an upgrade and the current air frames are fitted with these components

With all problems now solved the bell-cranks were reinstalled and it was at that point the rear spar attachment came into clear focus - one mounting hole was a figure 8 and the other only slightly better.






How 
The cause was forgetting that the factories had pre-cut in the attachment point through the deck plates at the stab installation, so both deck plates were clecoed back into position until that day.  [see below]

Why
As delivered
Many months passed assembling the fin, rudder,stab and elevators then finally the time arrived to install the components.

With the deck plates in position and displaying blank flanges visually reinforced a decision to level the tail plane so holes were marked onto the flanges allowing the components to be matched drilled after levelling the stab .

Note: These plates were riveted in position before commencing the match drilling further compounding the error

Santos from Flying Legend's insistence on removing the deck broke that error chain - this issue was not detectable, as both external holes appeared perfect and no inspection at the end of this project would have picked it up.

Note: The factory manuals have been upgraded  since my purchase now supplying assembly instructions based on the factory's own manufacturing procedures, The rear attachment requires it to be reamed and bolted up. 

Extract of information from new manuals supplied with kits
these are very detailed and cover the correct sequence of assembly 
with notes, 3D images and photos where required.


PRM = "Please read manual"


Fix
The first task was to remove the the stiffeners attached to the bulkhead and they had been solid riveted. Without putting too fine a point on it, many hours were spent removing these six [6] rivets with the final method required the flared end to be ground back using a Dremel Motor Tool and drilling holes through the rivets until the reinforcing plates could be freed.

Note: On examination the rivets were fused to the bulkhead material at their junctions  - interesting

With both plates removed the front plate was salvaged to be used as a drilling template. New plates were cut using a scroll saw and finished using a combination of power sander and hand files. Finally all edges were then polished using 400 grit aluminium open cut paper. 

The factory they sent photos of the current installation for clarification and it showed the rivets were now five [5] off per side and all in a straight  line - done - scrap the first one. A quick referral to the new manual and drawings allowed a new profile to be developed.


New stiffeners - red stuff is blood - mine 

Stiffener finally in position
A packer [2 mm] was placed under the lower attachment point



Current factory installation
So more sawing, filing, sanding and alodine treatment  there was a new set of stiffeners. The  bolts were fitted with clecoes in the original holes, finally all the rivet holes were drilled to 5/32'' to ensure clean holes. Not having a riveter Steve from the hanger down the row stepped up and gave me a quick lesson on riveting solids.

Note: This was done twice as I was not 110% happy with the first brackets and decided to upgrade to match the current factory arrangement as it allowed better access for riveting than the original shorter plate.


All swaf was removed and the stiffeners reassembled and the rivets installed.


Steve - Rivet Gun for hire
Thanks

Comment
When this blog started it would cover the good and bad this had the potential to be bad.

The rear attachment was upgraded with the fin attachment stab plus the work described.  Thi simple error created 30 hours plus in rework, re-manufacture of plates, fitting and refitting - hand work combined with the fear of compounding the error is not a fast way to work.


Closing this chapter a line from Forrest Gump comes to mind "stupid is as stupid does" -  so God is forced to cover stupid -  this would have never been seen by any inspection - I mean never.



Stupidity is not a excuse


Wing Hardpoints

This blog covers manufacture and installation of the external wing hardpoints.

Overview
One of the things that change the Tucano into a military replica was the factory's addition of under wing tanks and it was decided this Tucano was to have a set. These tanks can be used as additional luggage or fuel tanks offering 25 liters per side. 

As the factory is yet to finalize their design so to some degree I am on my own devices to proceed.

Read disclaimer page

Manufacture
The factory has supplied drawings to manufacture the hard points from 0.160'' aluminium to mount underwing storage and these are custom profiles to suit this aircraft. Once completed DXF files were sent out for laser cutting, when received all parts were de-burred and alodined.
Brackets and tanks
Note these tanks are just drawings as
the fuel tanks are a way off



Installation
The rear bracket was installed by locating it about the center of the lighting hole in the rib. Once located a length of aluminium was drilled at the required mounting distances and bolted to both hard points. The front point was then swung into position on the rib and match drilled.


Front mount with aluminium spacer


Rear mount secured for drilling

With all holes drilled the parts were removed - deburred and then fixed using 3.2 mm OD multi grip rivets.



The next task was to slot the skins to accept the hard points, cardboard templates were created using the mounting holes on the rib locating the lug in reference to the rivet holes as locating points. The profiles were then marked onto the skin using a cardboard template referenced to the matching rivet holes in the skin allowing it to be marked onto the outside of the skin.

The slot was marked and filed to clear the mounting point with the gap to be sealed with a silicone fillet at final assembly.


Cardboard jig and skin slotting

Finished installation

Port Wing Installation
Installing the points on the opposite wing followed the same procedure BUT a jig was used to set the location of the rear hardpoint to allow any tanks to fit either wing.




The jig was a length of 25 x 25 x 1.5 aluminium angle from the hardware store that was match drilled to the starboard installation, then the nose attachment was installed with reference to the starboard side.

Next, the jig was bolted to the nose attachment as was the rear attachment and then this assembly was swung into position after checking the starboard side the rear attachment was riveted into position.


Comments
None





Tuesday, 3 April 2018

Muffler Fix

This blog covers the work to fix the muffler as outlined in a previous blog.

Overview
The muffler has to be rectified as the installation needs the compact design and the weight saving that is more than welcome. 

Rework
The first problem was to remove the side plates with the inspection opening showing that this was possible. After a number of different approaches with the best using a 4'' grinder with cutting disk to remove approximately 50% of the flange and finishing with a grinding wheel. A few blows with a soft hammer and the flange broke free.

The penetration from the bead weld is better than a mm and the standard of workmanship from the welder / fabrication is without fault - design is another issue.


Modifications shown in red
After modification it will become only a resonator box

Once the modifications were done the components were bundled up and set out for re-welding.

Comment

Me Too